SR1 construction update – 24 Hours/Day – 7 Days Per Week Construction to Begin May 31, 2023

June 9, 2023 by CRC Action Group in News

The following is a message from the Springbank Off-stream Reservoir Project Team distributed on May 31, 2023. This construction season, an estimated 3.5 million cubic metres of fill material will be moved as part of construction of the Springbank Off-stream Dam Project. This requires the movement of 35,000 cubic metres of fill material daily. The contractor will need to use all good weather days to complete this work. Beginning May 31, 2023, earthwork operations will […]